Status Update - 1/31/19
January 31, 2019
| Status Item | Current Status | Previous Status | Comment |
| Schedule | red | red | 2 Weeks behind on build |
| Resources | green | green | |
| Financials | yellow | yellow | Small variance of actual vs budgeted hours requirement review activities |
| Quality | green | green | |
| Project Issues | yellow | yellow | 1 month delayed on requirement sign-off |
| Key Deliverables | % | Comments | Timeline |
| Requirement Sign-off | 60% | In Progress | 12/14 |
| Data Model/Mapping | 72% | In Progress | 1/12 |
| Build | 37% | In Progress | 3/28 |
| Training/UAT | 0% | Not Started | 4/1 |
For the detailed January 31, 2019 status report, click here.