Status Update - 1/31/19
January 31, 2019
Status Item | Current Status | Previous Status | Comment |
Schedule | red | red | 2 Weeks behind on build |
Resources | green | green | |
Financials | yellow | yellow | Small variance of actual vs budgeted hours requirement review activities |
Quality | green | green | |
Project Issues | yellow | yellow | 1 month delayed on requirement sign-off |
Key Deliverables | % | Comments | Timeline |
Requirement Sign-off | 60% | In Progress | 12/14 |
Data Model/Mapping | 72% | In Progress | 1/12 |
Build | 37% | In Progress | 3/28 |
Training/UAT | 0% | Not Started | 4/1 |
For the detailed January 31, 2019 status report, click here.